Annex I

Assessment
Report
Complaint filed to the CAO
regarding the
September 2001
Office of the Compliance Advisor/Ombudsman of the International Finance Corporation
and the Multilateral Investment Guarantee Agency
The Complaint dated
The CAO appraised and accepted the Complaint and thereby informed the Complainant
by way of facsimile, Mr. Muramuzi Frank, President
of NAPE on the
1. The Complaint
The Complaint raised issues that the CAO viewed as complex and interrelated.
The CAO concluded several issues fall under the Ombudsman role, and the other
issues would be better dealt with under the Advisory role.
Several issues raised by the Complainant referred directly to the activities
of IDA. CAO suggested that these matters could be best referred to the Inspection
Panel.
The Complaint also referred to issues of corruption and bribery. The CAO referred
the Complainant to the World Bank’s Fraud and Corruption Unit.
The CAO attended as an observer, the Public Consultations on the EIA, held
at
The CAO response to NAPE on the
In its Ombudsman role, the CAO has formally raised nine issues with IFC, and
has met with the Project Team to go through the issues. The CAO has read the
summary of the public consultation at Jinja, Uganda
on June 12, 2001, and the summary of the Second International
Forum on the Proposed Bujagali Hydropower Project, Washington, DC, July 17-18, 2001, relevant portions of the EIA, and related documents
The Complaint focuses on broader issues related to the economic viability
of the project, the cost to consumers, and the benefit to the people of Uganda.
It also raises key issues raised by the World Commission on Dams (WCD) guidelines.
The CAO has asked the IFC to comment and reply directly to the Complainant.
2. Background
The Complaint arises from citizens’ concerns about the proposed Bujagali Hydropower
project, a 250 MW hydropower facility
being proposed on the
The project sponsor is AES Nile Power (AESNP), a company formed by the AES
Corporation of
As part of the Bujagali project, electrical transmission facilities are proposed,
to enable connection to the Ugandan electrical grid.
The World Bank Group’s involvement in this project will be through the IFC
providing finance and IDA providing credit guarantees. The environmental and
social “safeguard” policies of the IFC are therefore applied. Supervision
of the implementation of the safeguard policies will be the responsibility
of the officers of the Technical and Environment Department at IFC. Review
of the environmental and social issues of Bujagali hydropower project began
in 1998.
The EIA was released in April 2001, locally and in
As the World Commission on Dams (WCD) report has been released, the Bujagali
project is seen as a benchmark for the construction of dams.
3. Situation Assessment
IFC in
IFC project preparation: The Bujagali project was created in 1997. Bujagali is the first hydropower project in
Issues of finding best, least-cost, options for developing power in
How thoroughly were alternate energy sources examined? Acres International
was commissioned by the WBG to undertake a comprehensive assessment and least-cost
analysis of all practical alternatives for meeting
Related to the examination and assessment of alternative energy sources is
the issue of hydrological flow rates and risk, and their role in ranking alternatives;
if water flow in the Victoria Nile River is below a certain level, payment
during the first 12 years, when debt is
outstanding, are reduced. However, if water flow rates drop significantly,
but don’t drop far enough to trigger the hydrological force majeure
protections, then the Ugandan government would still be forced to pay AES
for far less electricity than originally foreseen.
Another issue relates to determining the best, least-cost alternative involving
tourism on the Nile, especially white water rafting. The Ugandan Tourism Association
insists that the EIA severely underestimates the size of the rafting enterprises
in particular, and tourism activities in general, on the local economy. Therefore
they agree another economic aspect of building a dam at Bujagali has been
underreported. The end result of both hydrological risk analysis and tourism
income is that the EIA does not include a true picture of the costs and benefits
of a major hydroelectric installation at Bujagali.
Comprehensive study of cumulative impact of a cascade of
dams along the
One observation from this study was that there is a desire in
What is the rationale behind the Kalagala offset?
The Bujagali reservoir would permanently inundate
How exhaustive was the consultation process with local communities? AES Nile
Power has carried out 254 meetings with local
residents from affected areas; 61 meetings with representatives
of cultural institutions; 354 meetings with local
and GOU representatives; 146 meetings with stakeholders;
139 meetings with environmentalists
and NGOs; 32 meetings with lenders;
and 159 meetings with others,
plus 185 consultations with national
media. Stakeholder forums were held in
In-country consultations were “witnessed” by a third-party NGO, InterAid. InterAid
Does compensation and resettlement of project-affected people carried
out by AES pre-empt decision-making processes by IFC, WBG, & GOU? According
to IFC, commencement of implementation of the Resettlement and Community Development
Action Plan (RCDP) does not pre-empt IFC decision-making. AES has made the
decision to implement the RCDP on the basis of National Environment Management
Authority (NEMA) approval; IFC has provided a list of resettlement consultants
and reviewed drafts of the RCDP. IFC advised AES that implementation of the
RCDP before issuance of IFC’s Environmental and
Social Clearance would be done at AES’ own risk. This is confusing to outside
parties, contradicts IFC’s assertion of its leverage
at this stage of a project, and reveals a weakness in the IFC system.
Who was consulted on the spiritual significance of the
Has there been a comprehensive management plant done for the
Will there be a separate approval process for the transmission lines before
the project is approved? IFC insists that the decision to have separate public
hearings on the transmission lines was fully NEMA’s
decision. Some stakeholders feel that IFC’s release
of the transmission line EIA before NEMA’s approval
of that document put pressure on NEMA to approve it. (NEMA approved the Transmission
Line EIA on uly 18, 2000). However, IFC release of the EIA does not indicate
WBG approval of the project, and the WBG is obligated to measure the EIA against
it’s own safeguard policies.
Will the PPA for the project be made available to the public, and what is
IFC’s position about a public release of the PPA? IFC insists
that the PPA is a confidential agreement between AES Nile Power and the GOU—and
IFC is not a party to this agreement. IFC’s position
is that its release of the PPA to the public would violate the IFC information
disclosure policy. NGO’s point out that it is difficult if not impossible
to have a useful discussion regarding the economic implications of Bujagali
without access to the PPA. Furthermore if AES wants to maintain a degree of
secrecy consistent with a private sector project, perhaps public institutions
should not be asked to provide guarantees for or subsidize the undertaking.
4. CAO Conclusions
The CAO assessment is limited to the issues raised and accepted in its Ombudsman
role, however it is aware of the broader concerns that relate to the Bujagali
Hydropower project. The EIA has provided the substance for comment and questions
by the stakeholders both in and outside of
The CAO is satisfied that whilst the project is still in the pre-Board approval
stage, and the sponsor is awaiting a decision by the IFC regarding its involvement
in this project, the staff of the IFC’s Environment Department have maintained a close
watch, and have been diligent in ensuring that the sponsor complies with the
IFC safeguard policies.
There remain outstanding issues:
5. Suggested path forward
or recommendations
The CAO is aware that there is a request to the Inspection Panel.
The CAO now needs the Complainant to consider the assessment of the Ombudsman
and comments by IFC management [under the CAO’s
Advisory role] and request further intervention, if necessary. The CAO does
not see a role for facilitation or mediation at this stage because the IFC
has not made a final decision to participate in the project.
Source: Email from Nape SBC [napesbc@afsat.com]